Seven months down and two to go!  The site is feeling very active and busy with lots of different trades now on site.  This Wednesday had over a dozen busy bees set about their various tasks.  On the outside, the slate and the saranfil single ply membrane roof are now complete and all the windows are fitted.   The external stonework is about half way there.  It’s fitting into the context really well, as the stone has a good variation of colour.  The 25mm recessed pointing really picks out the horizontality of the stone and Beatrice’s coursing works really well.   The red cedar timber shingles, and their aroma, are on site and tantalisingly stacked up in the car port, and will start to go on next week after the flashings have been delivered and fixed.  The copper on the tower again will start next week.  The aim is for the scaffolding to be down in 3 weeks time which will be very exciting.  Internally, the ramp has been completed, and there is a real spatial delight in moving through a space in a changing vertical position.  The air guard system is being fixed and sealed, and will minimise any air leakage and associated heat loss.  From what looked like a simple and compact electrical system, a spaghetti like network of cables af first fix has evolved.  Internal partitions are also going up and being sheeted, starting to sculpt and refine the space into a hierarchy.  This week has also seen blacksmiths on site in the form of Ian’s Dad, making all the internal and external balustrades out of the 250kg of cold rolled 6m steel length which were mistakenly delivered to our house and had to be stored for a week in the back garden.  The first section of the metalwork is complete, with a simple staggered hit miss repeat of circular and flat bar, which gives an additional dynamic when moving along the ramp.
So all we need now is some moving boxes!

first Caithness wall

Stone:  Jura and Caithness

On the ground floor at the front of the building and around the entrance we are using Caithness stone.  Although from the very north of Scotland, it’s used to pave the streets of Edinburgh.

The Stone itself is extracted from a 3m high bed which lies under 4.5 – 9m of overburden. Caithness Flagstone is quarried from 16 principle layers split into a total of 49 individual flagstones, ranging in thickness between 20mm and 80mm .  It is from the Old Red Sandstone of Devonian age (370 million years old).

Stone can be expensive as a raw material and also in its laying.  To try and negotiate this fact, we used offcuts from paving stones which are in effect the ‘trimmings’.  These still need to be sawn cut to regularise them, but are about a third in cost of the riven faced stone.  The difficulty in laying comes from the varying heights of the stone which is a by-product of the natural bed thickness and requires the skill of a stonemason to piece the wall together.  Given the typical paving thicknesses are 40, 60 and 80mm, we decided to use these thicknesses to form courses similar to brickwork but at varying random lengths.  Beatrice came up with 4 coursing patterns and chose her favourite – which is being built (She also chose the purple window).  We like the horizontality of this layering and it is reminiscent of paintings by Caspar David Freidrich the German Romantic Landscape painter.

Visiting a Jura quarry just north of Munich for a commercial office project, the ‘travertine’ cut blocks, which cut the stone ‘through the bed’, were an extraordinary visual cross section through the earth itself.

Jura Limestone (meaning from the Jurassic period) contains visual fossilised evidence of the natural world as it was in the Mesozoic age approximately 150 million years ago.  Limestone is a sedimentary rock formed by layers of marine organisms deposited on the sea floor and compressed to create a stone with a variety of surface markings, meaning it is normally bed cut to uncover these natural formations such as Ammonites, Belemnites, Quartz Veins, Sponges, Corals and Feather Stars.  There are 22 layers or ‘beds’.

We’re using this in the wetroom, which is unusual as the stone is porus, however the quarry were able to source a much denser stone for this purpose (apparently a much younger stone which seems counter intuitive).  As a finish it has a 220 hone on the walls, and an 80 hone on the floor to provide a good slip resistance.

Having visited the quarry and being able to see and understand the product and production process, allowed us to order direct, which kept the costs tight (saying that a considerable percentage went to the haulage firm) and afforded us the Jura for the price of a mid-range ceramic tile.  It should be arriving on site in the next week or so.


I have always been interested in left over spaces in buildings: I have seen children delighting in using these spaces. Having a ramp meandering its way around a two story house, there are lots of left over spaces created. Some of these we are only becoming really aware of as the building progresses, despite having designed with models, which should have revealed them all, but the reality of this variety of people sized spaces is constantly surprising us. We designed so that every turn in the ramp would create its own unique pausing space: the reality of this, will only become clear once we use the space


here is the 3D image from the beginning of the week. I will publish another one at the weekend of how it looks now, for a spot the difference. If you can look at this on an iPad /Pod / Phone it feels like you are in the space.


There’s something about windows that have a very finished feel to them. Something to look out of, at the very least.

20120817-130249.jpg

20120817-130324.jpg

20120817-130346.jpg

20120817-130402.jpg

20120817-130414.jpg

20120817-130429.jpg
And a front door!

20120817-130602.jpg